PAST PERFORMANCE - To better serve a population that is expanding to the north
side of Peoria, Methodist Medical Center (MMC) decided to construct this state-of-the-art outpatient center. The facility provides a wide variety of health care services
including physical therapy, laboratory testing, an imaging center and several
doctors’ offices. The building is actually
owned by DASCO, a well-known medical real estate developer and
leased to MMC. Methodist was intent that this project help them take a leap in technology. The facility implemented an electronic medical record system and employed the latest medical imaging
technology.
Since the DASCO Company is a national developer, P.J. Hoerr had
to successfully compete against several local and national construction management
firms to be awarded this project.
Services required included pre-construction estimating, scheduling and
consultation on construction details and materials. Our team attended numerous
pre-construction meetings over several months to aid in finalizing the design.
P.J. Hoerr then managed the bidding of the project and developed a Guaranteed
Maximum Price (GMP) for the core and shell of the building and began
construction. Once the interiors were designed, approximately four months
later, those drawings were also bid. The P.J. Hoerr team then managed
construction of the building and installation of much of the complicated
imaging equipment. The GMP for the project ended up 0.9% greater than the
conceptual estimate provided to the Owner seven months earlier. The final costs
for the project were approximately $440,000 below the GMP, all of which were credited to the Owner.
This project was definitely on a fast-track schedule as much
of the interior design was not completed until only weeks or months before
scheduled project completion. Schedule was extremely important to the Owner and the
contract required a penalty of $3,500 per day liquidated damages for late
completion. P.J. Hoerr met the very aggressive schedule (even with dozens of
last minute additions and changes) and completed the core/shell
construction in 12 months and completed all the interiors in an additional
3 months.
No comments:
Post a Comment
Thanks for commenting on pjhoerr.blogspot.com