OSF Saint Clare Family Health Center - Washington, IL

This project consists of an 11,000 sq.ft addition and 30,000 sq.ft. of interior renovations.
Currently interior mechanical demolition and rough in is under way and some interior finishes are being completed in two offices (paint, carpet, base board). Exterior building demolition is completed and site work utilities are being installed. Foundations will start going in next week.